Alaska repairs earthquake-damaged roads ‘in record time’

Earthquake Damaged Road

Alaska has made fixings to it’s roads and bridges in record hour since the Nov. 30 earthquake deep beneath Anchorage and the Mat-Su Valley.

That’s thanks to a quick replies from the president and Federal Highway Administration, according to the commissioner of Alaska Department of Transportation& Public Facility( DOT& PF ).

“We look forward to working with FHWA on most robust repair of infrastructure facilities this summer, ” Commissioner says John MacKinnon says in a press release.

The restoration of the Glenn Highway northbound and southbound lanes by early Dec. 5 reopened essential trip routes.

DOT& PF employees and Alaska contractors” have worked tirelessly to re-establish crucial transportation relates ,” points out Gov. Mike Dunleavy in a press release. “Regardless of the challenges, they have committed to finding solutions in register time.”

The 7.0 importance earthquake struck at 8: 29 a.m. Nov. 30, making extensive property and infrastructure shattering but claiming no lives. No serious injuries were reported, either.

Even as aftershocks followed, Alaska’s transportation department immediately shifted into high gear.

Crews swiftly deployed to inspect roads and bridges, receiving earthquake damage severe and widespread in some areas. On the day of the earthquake, DOT& PF proved dot.alaska.gov/ earthquake2 018 for online situation updates.

Infrastructure and related situations were posted as soon as they were confirmed.

” The Glenn Highway Mirror Lake area was particularly difficult to fixing because it was a decide of two great sink gap that encroached into the northbound and southbound lanes ,” the department says.

” Subsequent aftershocks expanded the sloughing well into both lanes. DOT& PF is confident that the temporary fixings have been completed will ensure the safety of the traveling public .”

Road Damage from Earthquake Aftermath

Winter construction has been particularly difficult with frozen clay and temperature-related challenges in paving and painting.

While the thrust of repair work has been to restore essential travel, the department says it will engage permanent restores next summer.

The department will continue identifying shattering areas, induce fixings and plan for permanent secures. Because the immediate fixings have been focused on rehabilitating travel, they are not expected to have a 20 -year life cycle, which is something that the government expects from typical highway construction.

Highway

Seward Highway at Tudor after repairs.

” The rapid response to damage in Anchorage shows how investing time and fund into the process of preparing this form of large-scale, infrastructure-hobbling occurrences can pay off in the long-run, even when there’s no way to tell when or where calamity may strike ,” says an article published the coming week at The Verge.

Read more: equipmentworld.com